Karnataka Expansion Watch, 24 June 2026 (free sample)

Free sample issue, 24 June 2026, Enosh Infra

Every month we list the new ventures coming to the industrial corridors in and around Bengaluru that our clients ask about, so you hear of them before they start looking for space.

21approvals and recommendations
337acres, about
Rs 4,204 Crstated investment
8,227jobs stated

Where the approvals are

Each circle is a corridor around Bengaluru, sized by acres on file in this issue. Select one to jump to it. Not to scale.

about 70 kmDoddaballapura34Devanahalli27Tumakuru20Kolar215Hoskote34Jigani, Bommasandra7Bengaluru

Acres on file, by corridor

All stages, as approved

Kolar215Doddaballapura34Hoskote34Devanahalli27Tumakuru20Jigani, Bommasandra7

Where each file stands

Number of units by stage

ApprovedExtension or change
DoddaballapuraApproved: 77DevanahalliExtension or change: 33TumakuruExtension or change: 11KolarApproved: 5Extension or change: 16HoskoteApproved: 22Jigani, BommasandraApproved: 1Extension or change: 12

Names to watch

DoddaballapuraSFO TechnologiesGot 7 of 25 acres asked

The rest of the requirement goes looking for leased space.

DevanahalliVivek Power TronicsFactory plot to plug and play space

An allottee choosing rentable space over its own factory says where the demand is.

HoskoteYJ Link IndiaBought a resale plot, 4.56 acres

Buying instead of waiting for allotment means they want to start soon.

KolarInnovative Fab SystemsGot 3 of 13 acres asked

A short allotment like this usually turns into a lease enquiry.

This month in one minute

  • Four park and logistics developers hold approvals for about 200 acres around Kolar, three of them new, and RMZ adds about 30 acres at Hoskote. That is competing supply for anyone holding sheds on that side.
  • Adinarayanahosahalli near Doddaballapura is the busiest single address. Seven units were approved there in one meeting, from liquid oxygen to satellites.
  • Near the airport, a medical electronics plot in the Aerospace Park is switching to a plug and play IT park.
  • The companies below have been planning for months. Most of them still need somewhere to work while they build.

Investment and jobs are what the companies stated. Acres are what was approved, which is sometimes less than was asked for.

Doddaballapura and Adinarayanahosahalli

7 items
34 acresLargest: SFO Technologies
See all 7 rows
CompanyApproved forAcresRs CrJobsStage
SFO TechnologiesElectronic and machined parts, metal finishing for aerospace7 (asked 25.49)4902,500ApprovedApproved. Land from the Science Park reserve, Adinarayanahosahalli Phase 2
Bellatrix AerospaceSpacecraft, satellites and launch vehicles4.15404339ApprovedApproved, Adinarayanahosahalli Phase 1
Praxair IndiaLiquid oxygen and nitrogen5 (asked 6)21040ApprovedApproved, Phase 2
Bulk Liquid SolutionsFlexi tanks and FIBC bags for export8110735ApprovedApproved, Phase 2 SEZ
JJG Special ProcessingAerospace special processing280250ApprovedApproved, Phase 2 SEZ
Synthesis Winding TechnologiesCapital equipment for winding6.5 (asked 7)71.75250ApprovedApproved, Phase 2
Rhewum IndiaExpansion: screening machines, conveyors, spares1.516.580ApprovedApproved, Phase 2 SEZ

What it means

  1. Adinarayanahosahalli has turned into an aerospace and electronics address. Seven units cleared in one meeting is a cluster forming.
  2. Most of these plots are 2 to 8 acres and none is built yet. Expect requests for 10,000 to 40,000 sq ft of ready space nearby while the factories go up.
  3. SFO asked for 25 acres and got 7. When a company gets less than a third of what it asked for, the rest of the requirement goes looking for leased space.
  4. Landlords around Doddaballapur with good power and clear height should expect calls from aerospace suppliers first.

See warehouse and shed rents at Doddaballapura.

Aerospace Park and Devanahalli

3 items
27 acresLargest: Brigade Estates and Projects
See all 3 rows
CompanyApproved forAcresRs CrJobsStage
Brigade Estates and ProjectsAerospace and defence components25475Not statedTwo more years to build, a five star hotel added to the plan
Innomech Aerospace ToolingsChange of use to manufacturing plus a free trade warehouse0.6120Not statedChange approved, subject to SEZ rules
Vivek Power TronicsChange from medical electronics to a plug and play IT park116.41Not statedChange of activity and two more years to build recommended, Hi-Tech Defence and Aerospace Park

What it means

  1. Vivek Power Tronics is turning a medical electronics plot in the Aerospace Park into a plug and play IT park.
  2. When an allottee changes activity to plug and play space, it says the area pays more as rentable space than as its own factory.
  3. Brigade's 25 acre aerospace plot has two more years to build, so that supply is not arriving soon.
  4. Innomech adding a free trade warehouse points to bonded storage demand near the airport.

See warehouse and shed rents at Devanahalli.

Tumakuru, Vasanthanarasapura and Dabaspet

1 item
20 acresLargest: DhaSh PV Technologies
See all 1 rows
CompanyApproved forAcresRs CrJobsStage
DhaSh PV TechnologiesSolar junction boxes, cables, connectors20346.35 to 490Not statedApproval moved to a group company, project cost revised

What it means

  1. Only one item this time: DhaSh PV moved its solar component approval to a group company and revised the cost.
  2. A change of holder is not new demand, but it shows the project is still alive. Watch for a start on site.

See warehouse and shed rents at Dabaspet.

Kolar, Narasapura, Vemagal and Malur

6 items
215 acresLargest: Orbit Industrial Park
See all 6 rows
CompanyApproved forAcresRs CrJobsStage
Orbit Industrial ParkLogistics and industrial park30 (asked 40)4541,100ApprovedApproved, Bavanahalli
Hikaru IAL AssetIndustrial park, warehousing, logistics30 (asked 61.4)422.69600ApprovedApproved, KGF Industrial Area
Aequs Industrial Park IIIndustrial park100221.20Not statedTransfer of approval from Aequs SEZ ratified, KGF
Aries RefineryPrecious metal concentrate processing14157.45300ApprovedApproved, Bavanahalli
Jurojin DevelopersIndustrial and logistics park38.21371,500ApprovedApproved. Includes about 30,780 sq m already built at Narasapura
Innovative Fab SystemsFacade systems, windows, steel structures3 (asked 13)49200ApprovedApproved, KGF

What it means

  1. Four park and logistics developers hold approvals for about 200 acres here, three of them new this time. That is competing supply for anyone holding sheds towards Kolar.
  2. Parks this size take two to three years to deliver finished sheds, so the near term effect is on land prices, not rents.
  3. Aries Refinery and Innovative Fab Systems are occupiers, not developers. Innovative Fab asked for 13 acres and got 3, so it may need leased space for the rest.
  4. Jurojin's approval includes about 30,780 sq m already built at Narasapura, the one piece of supply here that is close to ready.

See rents on this corridor in our rate index.

Hoskote

2 items
34 acresLargest: RMZ I&L Project (Hoskote)
See all 2 rows
CompanyApproved forAcresRs CrJobsStage
RMZ I&L Project (Hoskote)Industrial and logistics park29.9, own land198.62100ApprovedApproved, M. Hosahalli, Nandagudi Hobli
YJ Link India (Korea)SMT automation equipment4.56, bought177.96173ApprovedApproved. Plot at Chokkahalli bought from another KIADB allottee

What it means

  1. YJ Link, a Korean equipment maker, bought a 4.56 acre plot from another allottee at Chokkahalli. Buying a resale plot is the fast route, and it means they want to be running soon.
  2. RMZ adds an industrial and logistics park of about 30 acres on its own land near Nandagudi. That is future supply on the Hoskote side.
  3. Hoskote stays a logistics first corridor. Small manufacturers here compete with warehouse tenants for the same sheds.

See warehouse and shed rents at Hoskote.

South: Jigani, Attibele and Bommasandra

2 items
7 acresLargest: Laxmi Steel Overseas
See all 2 rows
CompanyApproved forAcresRs CrJobsStage
Laxmi Steel OverseasWarehousing for FMCG, electronics, pharma and furnitureAbout 5 (20,391 sq m), own KIADB land29.7760ApprovedApproved, Bommasandra
Lake ChemicalsBulk drugsAbout 2 (7,998 sq m)16.10Not statedTwo more years to build

What it means

  1. Laxmi Steel Overseas is building warehousing for FMCG, electronics, pharma and furniture on its own land at Bommasandra, about 5 acres.
  2. Lake Chemicals got two more years to build. Delays like this keep pressure on existing ready space in Jigani and Bommasandra.
  3. The south corridor is mostly full, so new supply comes in small pieces. Ready sheds here keep their pricing.

See warehouse and shed rents at Jigani, warehouse and shed rents at Anekal, warehouse and shed rents at Bommasandra.

How to read this issue

  • Approved means the project has State approval for its land. Recommended means it has passed an earlier review and a final decision is still to come. Deferred means it will come back.
  • We list companies only. We never publish the names of promoters, directors or officials.
  • Investment and job numbers are what the company stated. Many projects take years, and some never happen. Use this as an early signal, not a promise.

Get next month's issue. If this helped, send it to someone who owns or leases industrial space around Bengaluru. Questions about space in any of these corridors? Talk to us.

Investment and jobs are as stated by the companies. Not investment advice.

Enosh Infra, industrial and warehouse space around Bengaluru since 2019, from 10,000 to more than 400,000 sq ft. www.enoshinfra.com